Firm vs Intermittent
Understanding the difference between always-on power and weather-dependent generation.
Three Different Numbers, One Power Station
When someone says "NZ has 10,000 MW of generation capacity," what does that actually mean? Here's why the answer is more complicated than it sounds:
A Visual Example: 100 MW Wind Farm
What you can count on during a calm winter evening peak
Typical output across the year (~35% capacity factor)
This doesn't mean wind is "bad" — it means we need to understand what different generation types actually contribute to the system.
Capacity Factors by Generation Type
The capacity factor is the ratio of actual output to maximum possible output. It varies dramatically by technology:
| Technology | NZ Nameplate | Capacity Factor | Factor Visual | Firm Contribution |
|---|---|---|---|---|
| 🌋 Geothermal | ~1,050 MW | ~90-95% | Very high — runs 24/7 | |
| 💧 Hydro (with storage) | ~5,400 MW | ~50-55% | High — dispatchable on demand | |
| 🔥 Gas peakers | ~1,500 MW | ~10-30% | Very high — runs only when needed | |
| 💨 Wind | ~1,200 MW | ~35-40% | Low — can't guarantee availability | |
| ☀️ Solar (utility) | ~800 MW | ~12-18% | Very low — zero at peak (evening) | |
| 🪨 Coal (Huntly) | ~500 MW | ~20-40% | High — dry year/winter backup |
Capacity factors are NZ-specific estimates based on Electricity Authority and MBIE data, 2023-24. Actual varies by site and year.
Why This Matters for NZ's Energy Transition
NZ has a massive pipeline of new generation — 289 projects totalling 44 GW of nameplate capacity. But 82% of that is wind and solar. This creates two important dynamics:
✓ Energy abundance
Wind and solar are excellent at producing cheap energy (GWh). Over a year, a 100 MW wind farm might produce as much energy as a 35 MW baseload plant running 24/7. More renewables = more total energy = lower average prices.
⚠ Capacity challenge
But wind and solar can't guarantee capacity (MW) at peak times. On a calm winter evening at 6pm, solar output is zero and wind might be 10% of nameplate. Something else must fill the gap.
The Transition Challenge
As NZ adds more intermittent generation and retires thermal plants, we face a question: what provides firm capacity when renewables can't?
- Hydro with storage — Our primary flexible resource, but limited by water availability and increasingly needed for firming rather than baseload
- Batteries — Growing fast, but current grid-scale batteries provide 1-4 hours of storage, not days or weeks
- Gas peakers — Reliable firm capacity, but gas supply is declining and emissions are a concern
- Demand response — Industrial users (like Tiwai) reducing load during peaks, but limited scale
- Imports — Not possible for NZ (island nation, no interconnectors)
NZ's Capacity vs Energy Reality
Here's how our current generation fleet breaks down — showing nameplate capacity vs actual contribution:
| Source | Nameplate MW | % of Capacity | % of Energy (2024) | Peak Contribution |
|---|---|---|---|---|
| 💧 Hydro | ~5,400 | 54% | 53% | ★★★★★ Primary flexible resource |
| 🌋 Geothermal | ~1,050 | 11% | 20% | ★★★★★ Always-on baseload |
| 🔥 Gas | ~1,500 | 15% | 9% | ★★★★★ Peak/emergency backup |
| 🪨 Coal | ~500 | 5% | 5% | ★★★★☆ Dry year backup |
| 💨 Wind | ~1,200 | 12% | 9% | ★★☆☆☆ Weather dependent |
| ☀️ Solar | ~800 | 8% | 1.4% | ★☆☆☆☆ Zero at evening peak |
Data: MBIE Energy in New Zealand 2024-25, Electricity Authority. Solar includes both utility and distributed.
The Firming Gap
As NZ builds more wind and solar while retiring thermal generation, a "firming gap" emerges — the difference between nameplate capacity and what's actually available during peak demand:
What Can Fill the Gap?
| Solution | Current Scale | Potential | Challenges |
|---|---|---|---|
| 🔋 Grid batteries | ~100 MW | ~6 GW pipeline | 1-4 hour duration; can't cover multi-day events |
| 📉 Demand response | ~300-500 MW | ~1,000+ MW | Limited industrial base; Tiwai uncertainty |
| 🔥 New gas peakers | Limited new build | Technically feasible | Gas supply declining; carbon liability; investment risk |
| 💧 New hydro | Limited sites | Some potential | Long consenting; environmental constraints |
| 🏔️ Pumped hydro (Onslow) | 0 | ~1,000 MW | Expensive; decade+ timeline; uncertain economics |
What Industry Is Debating
- Is "100% renewable by 2030" achievable and reliable?
- Should NZ build new gas peakers as a transition measure?
- Is Lake Onslow pumped hydro worth $15B+ for dry-year security?
- Can batteries + demand response + overbuild of renewables close the gap?
- Are current price spikes a market failure or an investment signal?
These are genuine questions without easy answers. Understanding firm capacity vs energy is the starting point for any informed position.
Sources: Transpower, Electricity Authority, MBIE EDGS 2024, industry analysis